Site Name: Hyde Farm     5 MW
Energy Type: Solar Photovoltaics
County: Buckinghamshire     Country: England     LPA: Milton Keynes Council
Site ID and Reference: 5685 /     District:
Applicant: Conergy     Application : 15/01791/FUL (Go to search to find Application)
--- For Solar Farms / Parks ---
Mounting of panels: Ground
--- ----- ---- ---
Site Address: Hyde Farm, Warrington Road, Olney
  MK46 4DU
County: Buckinghamshire Region: South East
OS Coordinates: 488765 / 488765
Development Status: Operational
Application Submitted: 8/7/2015 Planning Permission Granted
Application Determined: Permission refused:
Construction Date: 12/16/2016    
Generator Live 3/16/2017 This Record Last Updated: 4/26/2017
RO Banding (ROC/MWh) FiT Tariff (p/kWh):
  --- Additional Dates where relevant ----
Application Withdrawn:    
Permission Expiration Date: 1/12/2019    
Secretary of State - Appeal Lodged:
Called In: Appeal Withdrawn:
Refusal: Appeal Refused:
Granted: Appeal Granted: