Page views this IP this session = 1 of 5 unsubscribed pagesEascairt Wind Farm
Click here for Generation Forecast for wind farms based on Met office data
Subscribers see an interactive map with Eascairt Wind Farm and local projects displayed.
( Subscribe for £100 )to have full access to all Wind projects and details.
Subscribe to Wind for exact generator location including nearby generators
For an example of a wind project see: Little Cheyne Court Wind Farm
Subscribe for £500 to include full csv and KML downloads of all Wind project data.
To create a login account see: User Registration. This will allow 30 page views each session rather than 5
One subscription covers your organisation / school / university / company . NOT per user
|
Eascairt Wind Farm (Wind , Proposed) Location in the UK : Scotland, skipness Type of installation: Wind on/offshore: on Turbines :13 Capacity : 26 MW Approx Date of 1st power generation:
Subscribe to Renewables Map to see: Wind Turbines make / model / hub height / elevation / latitude and longitude. Accurate data available for 99% of all Active wind farms listed, also cross reference to DECC and OFGEM datasets
Wind Turbines, Wind Farm, Renewable Energy, Green Power
/YES
Erection of windfarm comprising 13 wind turbines (maximum height of 100 metres) together with ancillary infrastructure including a permanent wind monitoring mast, access tracks, crane hardstandings, substations, control building, temporary construction compound and borrow pit search areas For Wind projects, Subscribed version includes Turbine data, average hub height, average elevation Subscriber Register Escairt Farm by Skipness
Please note that where multiple DECC rcords are available, all are shown in order. eg Project then repowering / extension, or refused project then resubmitted.
Site Name: |
Eascairt Wind Farm 26 MW
|
Energy Type: |
Wind Onshore |
County: |
Argyll and Bute Country: Scotland LPA: Argyll & Bute Council
|
Site ID and Reference: |
5123 /
District:
|
Applicant: |
Infinergy (formerly PI Renewables)
Application :
15/00205/PP
|
(Go to search to find Application) |
For Wind Farms |
|
Number of Turbines: |
13 |
Turbine Capacity: |
2 |
Height of Turbines: |
100 |
Calculated capacity: |
26 |
Site Address: |
Escairt Farm by Skipness
|
|
|
County: |
Argyll and Bute Region: Scotland
|
OS Coordinates: |
183500 / 183500
|
Development Status: |
Appeal Granted
|
Application Submitted: |
2/19/2015
|
Planning Permission Granted |
|
Application Determined: |
|
Permission refused: |
9/21/2016
|
Construction Date: |
|
|
|
Generator Live |
|
This Record Last Updated: |
5/26/2020
|
RO Banding (ROC/MWh) |
|
FiT Tariff (p/kWh): |
|
|
--- Additional Dates where relevant ---- |
Application Withdrawn: |
|
|
|
Permission Expiration Date: |
3/14/2027 |
|
|
Secretary of State - |
Appeal Lodged: |
12/20/2016 |
Called In: |
|
Appeal Withdrawn: |
|
Refusal: |
|
Appeal Refused: |
|
Granted: |
|
Appeal Granted: |
9/21/2016 |
Project Info |
Sorry I found no matches, Please try again.
|
|
©2018
Simon Mallett |
Latest News Added |
Carn Nicholas Drone footage Date and Time of entry: Tuesday, March 19, 2024 00:00
Carn Nicholas Solar Park The site, developed and constructed by Innova Renewables, was energised earlier this year following the beginning of its construction in May 2022. Date and Time of entry: Tuesday, March 19, 2024 00:00
Dorset Green Dorset Green H2 – South West’s first solar to green hydrogen production plant ready to produce clean, zero emission, green renewable energy Date and Time of entry: Tuesday, March 19, 2024 00:00
Dragon LNG Meadow
Date and Time of entry: Tuesday, March 19, 2024 00:00
Pretoria rd looking towards Ellistown.Solar farm.
Date and Time of entry: Tuesday, March 19, 2024 00:00
|
|
©2017
Simon Mallett |
|